Schedule

Schedule of the MultiMEMS MPW Runs

Infineon Technologies SensoNor offers two MultiMEMS MPW runs per year. The schedule of the current and incoming MPW runs is specified in the table below.

MPW Reservation
Date
Design
Submission Date
Delivery
Date
Status
Run 11 Delivered Current Run
Run 12 30.12.2008 15.05.2009 Next Run
Run 13 30.04.2009 20.05.2009 30.10.2009 Future Run
Run 14 Not Scheduled Not Scheduled Not Scheduled Future Run

NOTE: The schedule is subject to change.

LEGEND

Reservation Date: The date prior to which at least the filled-in and signed MPW Booking Form should be submitted.

Design Submission Date: The date prior to which the design, in GDS II format, must be submitted in its final form for inclusion on the next MultiMEMS MPW.

Delivery Date: The date prior to which the diced MultiMEMS wafers will be shipped to the individual customers.